Business Plans Archives - walloptutors https://walloptutors.blog/category/business-plans/ A+ writing Service. Wed, 29 May 2024 10:54:49 +0000 en-US hourly 1 https://wordpress.org/?v=6.5.5 233282827 Scenario You are in the tenth week of the XYZ Business Workflow project, and thi https://walloptutors.blog/scenarioyou-are-in-the-tenth-week-of-the-xyz-business-workflow-project-andthi/?utm_source=rss&utm_medium=rss&utm_campaign=scenarioyou-are-in-the-tenth-week-of-the-xyz-business-workflow-project-andthi Wed, 29 May 2024 10:54:49 +0000 https://walloptutors.blog/?p=1754118 Scenario You are in the tenth week of the XYZ Business Workflow project, and things haven’t quite gone according to plan. At the end of the requirements analysis phase, your team told you that:...

The post Scenario
You are in the tenth week of the XYZ Business Workflow project, and
thi
appeared first on walloptutors.

]]>
Scenario
You are in the tenth week of the XYZ Business Workflow project, and
things haven’t quite gone according to plan. At the end of the
requirements analysis phase, your team told you that:
Feature 2 (F2) development is more complex than thought initially. It will take at least 10 workweeks to be complete.
Feature Customization 3 (C3) will take close to five workweeks.
The complete system testing will take a minimum of one-and-a-half weeks due to the complexity of the systems involved.
You made some necessary resource and schedule adjustments in your plan and obtained stakeholder approval for the same.
However, due to delays in getting client approvals, UI design and
development took one week more than estimated, which has now pushed all
dependent tasks out by a week. Moreover, a resource availability issue
has added three days to the Feature 1 development effort.
You are scheduled to present a project status report at the end of
the week at a stakeholders’ meeting that will include the client’s
representatives.
Directions
Project Status Report
Create a presentation for
stakeholders describing relevant aspects of the current project status.
Your presentation must include the following: original and current
project schedule, current project status, updated risk register, and any
other relevant project information you believe the stakeholders need to
know. You can use any project management software (PMS) tool to create
and update the project schedule and status. However, remember to choose a
tool that will help you complete all parts of the project, like the
Gantt chart.
Specifically, your presentation must include the following:
General project information
Project goal and objectives
Team information
Initial schedule with milestones and end dates
Current project statusGantt chart that shows the project’s progress and current schedule
Updated risk/issues register that shows:
Status of risks from the project planning phase including whether
and how they have affected the project plan and schedule so far
Any issues facing the team currently and how you are managing them
Any new potential risks and proposed mitigation
Project summaryUpdated milestone and end dates
Action items to ensure the project stays on track
What to Submit
To complete this project, you must submit the following:
Project Status Report
Create a presentation of 8
to 12 slides to share the project status report at a stakeholders’
meeting. The presentation should include the basic project information,
current project status, updated risks and issues, and a project summary.